To 0.5 yd³ (about 22 eighty-pound bags) site mixing wins; 1–2 yd³ compares bags against a short load; over 2 yd³ orders ready-mix. A 13×10 ft slab at 6 in is 2.4 yd³ net and 2.6 with 7%: order 3 yd³.

Where is the breakpoint in cubic yards?

An 80 lb bag yields about 0.6 ft³: a yard needs about 45 bags. Past 20 bags mixing eats half a day and consistency drops.

Plants charge short-load fees and quarter-yard increments: 0.5 yd³ can bill like 1 yd³. The 0.5–1 yd³ band always compares case by case.

Ready-mix or bags by volume (guide)

Ready-mix or bags by volume (guide)
Volume80 lb bagsCall
Under 0.5 yd³to 22Bags (mix on site)
0.5–1 yd³22–45Compare: bags vs short load
1–2 yd³45–90Compare bags vs small ready-mix
Over 2 yd³over 90Ready-mix (order extra, pump when needed)

How is each shape cubed?

Slab is length × width × thickness. Strip footing is length × width × depth. Round column is πr²h. Solid stairs add steps as triangular prisms.

This guide estimates quantities. Depth, rebar and strength are signed by a qualified professional: this page never sizes structure.

slab V_ft³ = l × w × t ÷ 27 = yd³; order = V × (1 + 0.07), round up

What gets added besides volume?

Pumping when the truck cannot reach, formwork, rebar and blinding in trenches. None changes yd³, all change price.

In a trench, the strip footing covers volume (length × width × depth). Blinding, when used, quotes as its own 2–4 in line.

How do you order from the plant without error?

Order the 7% volume rounded up: 2.6 yd³ orders as 2.75 or 3 yd³. State design strength and slump, time and pump access.

Compare price per yard placed, not at the plant: haul and standby move the ranking between two plants.

Worked example: Slab 13×10 ft, 6 in thick

  1. V = 13 × 10 × 0.5 ft = 65 ft³ = 2.4 yd³
  2. At 7%: 2.4 × 1.07 = 2.6 yd³
  3. Round up: 3 yd³

→ Order 3 yd³ ready-mix (about 135 eighty-pound bags would be an unworkable site mix).

Common mistakes

From calculation to quote

Add labor, overhead and your margin, and generate the professional PDF.

FAQs

How many 80 lb bags make a yard?
About 45 bags (0.6 ft³ each). Past 1 yd³ price ready-mix even when mixing stays possible.
Does the calculator include rebar?
No: it cubes concrete only. Rebar, depth and strength follow the structural design.
Does it handle stairs and ramps?
Yes: stairs cube steps (tread × riser ÷ 2 × width × count) and ramps cube the wedge (length × rise ÷ 2 × width). Support slabs cube separately.
Pump or direct discharge?
When the truck cannot reach, add pumping as a line. Volume stays put, price moves (fixed service fee).
How do I compare bags vs ready-mix in dollars?
Multiply your bags (45 per yard) by bag price against short-load plus haul minimum. Without your yard prices no comparison holds.