Voltage drop calculator
System, load, voltage, run length, conductor size and material: you get voltage drop in volts and percent and the voltage at the load.
Voltage drop
2.9 %
- Voltage drop6.67 V
- Voltage drop (%)2.9 %
- Current16 A
- Voltage at the load223.33 V
Your prices per language/currency. Used when you enable “Use my prices” in calculators. My prices →
How it's calculated (visible formula)
single-phase: VD = 2 × L × I × PF ÷ (γ × A); three-phase: VD = √3 × L × I × PF ÷ (γ × A)
- Net geometric measurement, no waste.
- Adjustable waste % for cuts and breakage.
- Purchase rounded up to sellable units (boxes, bags, buckets, boards).
How to calculate it, step by step
- Choose single-phase or three-phase.
- Enter the load and voltage.
- Measure one-way cable length along the real route.
- Enter conductor size and material.
- Work out the drop and compare with the allowed maximum.
Worked example: 1,920 W on 120 V, 82 ft of 12 AWG (3.31 mm²) copper
- I = 16 A
- VD = 2 × 25 × 16 ÷ (48 × 3.31) ≈ 5 V
→ 4.2% — over the NEC's 3% recommendation; go to 10 AWG.
Common mistakes
- Forgetting the ×2 (out and back) on single-phase.
- Using 20 °C conductivity for loaded cable.
- Measuring run length on plan without drops and rises.
Pro tips
- Measure along the actual route, including rises and drops.
- If it's too high, upsize the wire.
- On long outdoor lighting runs, voltage drop usually governs over ampacity.
- Check the cumulative drop from the service too.
From calculation to quote
Add labor, overhead and your margin, and generate the professional PDF.
FAQs
- What voltage drop is acceptable?
- The NEC recommends 3% on branch circuits and 5% total.
- How do I reduce voltage drop?
- Upsize the wire or shorten the run.
- How do I convert AWG to mm²?
- 12 AWG = 3.31 mm², 10 AWG = 5.26 mm², 8 AWG = 8.37 mm².
- Does voltage drop waste energy?
- Yes — it is lost as heat in the wire (I × VD watts).
- What happens with excessive drop?
- Equipment underperforms, motors run hot and lights flicker.
- Does the neutral count?
- Yes — that's why single-phase uses ×2.